Methodology
Ventilation and odor control used:
6'x6' exhaust opening was installed to install 5 HP Blower, 6' x 6' was later constructed into a manhole.
Rehab method used:
Danby Panel Lok III-E Panels used, bottom, curved corner and top panel, finished with full annulus grouting with cementitious grout with minimum compressive strength of 6,000 psi.
Cleaning method used (if required) and who cleaned the line:
High pressure (8,000 psi) water blasting performed by Danby installer, Boyer, Inc.
Method of flow bypass or diversion, if used:
A diversion was installed to divert the flow to parallel box interceptor.
Hurdles
Problems encountered during construction:
Due to a crack in the crown, rehabilition was required prior to the General Contractors excavation and underpinning of Conduit as part of the construction of the newly rebuilt Back River WWTP. During cleaning, a crack along the floor revealed a cold joint which in turn lead to the discovery that the floor/walls were not a monolythic construction. Additional reinforcement was engineered, approved and installed to support the floor during excavation and underpinning.
Problems encountered after construction:
None