Methodology
                    
                        
                            Ventilation and odor control used:
                        
                        
                            Fresh air pumped into pipe past upstream air dam; maintained sealed lids during non-work periods, and adequate ventilation to carry odors downstream during the work periods.
                        
                     
                                        
                        
                            Rehab method used:
                        
                        
                            Danby Panel Lok III (spirally wound) with full annulus grouting with cementitious grout with minimum compressive strength of 5000 psi.
                        
                     
                                        
                        
                            Cleaning method used (if required) and who cleaned the line:
                        
                        
                            High pressure (3,000 - 10,000 psi) water blasting performed by the Danby licensee (Kinsel Industries Inc.).
                        
                     
                                        
                        
                            Method of flow bypass or diversion, if used:
                        
                        
                            Flows 100% diverted during work day, but reinstated during non-work periods.