Methodology
Ventilation and odor control used:
Not required (good natural ventilation).
Rehab method used:
Danby Panel Lok IIIE (84”) and Panel Lok III (72”) (spirally wound) with full annulus grouting with cementitious grout with minimum compressive strength of 5000 psi.
Cleaning method used (if required) and who cleaned the line:
High pressure (3,000 - 10,000 psi) water blasting performed by the Danby contractor (Houshour Inc.).
Method of flow bypass or diversion, if used:
None required.